Niger Delta clean up

ACTIVITIES OF HYPREP (HYDROCARBON POLLUTION REMEDIATION PROJECT)

Remediation work done at Lot 009 out of the five (5) outstanding Lots in Phase 1 Batch 1 Remediation Project Lots/Sites.

At Lot 009 (Saanako – Mogho, Gokana L.G.A), the Contractor has evacuated the dredged sand from the project site to a suitable part of the area and has already achieved more than half of excavation of impacted soil at the delineated area as well as treatment of parts thereof. The Monitoring {Quality Assurance / Quality Control (QAQC)} processes by HYPREP and the Contractor have already commenced, preparatory to backfilling of the large part of the excavated area.The other four (4) outstanding Phase 1 Batch 1 Remediation Lots (Lot 011 and 012 at Debon-Bodo/Mogho, Lot 013 at Nweekol Zorbuke –K.Dere and Lot 016 (Korokoro Well 005) are at present out of site awaiting completion processes for milestone payments

Information on Status of Remediation Works summarized in Table 1 Below:

 LOT NR. REMEDIATION CONTRACTOR SITE NAME L.G.A. PERFORMANCE PERCENTAGE (%)
009Odun Environmental Ltd Saanako, MoghoGokana68
011Mosvinny Nig LtdDebon- Bodo / MoghoGokana84
012Shamsa Resources & Services LtdDebon. Bodo / MoghoGokana89
013Centennial Devt. & Investments LtdNweekol Zorbuke, K.DereGokana83
016Newline West Africa LtdBuemene Korokoro Well 005Tai56

Close-out / Certification Sampling was completed at three (3) of the sites in Phase 1 Batch 1 in the period covered in this report. The sites include Lot 019 and 020 at Buemene Korokoro Well 8 in Tai L.G.A as well as Lot 014 (Nweekol Zorbuke, K.Dere in Gokana L.G.A). The Rivers State Ministry of Environment and Natural Resources (RMENR) and the Social Democracy Network (SDN) also participated in the process which is statutorily driven by the National Oil Spill Detection and Response Agency (NOSDRA).

Status of Phase 1 Batch 2 Sites

Setting up of site offices had begun at twenty-seven (27) out of the twenty-nine (29) Phase 1, Batch 2 remediation sites {the two (2) pending Lots in this category are Lot 027 at Bara Alue, Tai L.G.A and Lot 032 at B.Dere / Gio, Gokana / Tai L.G.As}. 

Seventeen (17) of the twenty-nine (29) lots in Batch 2 have either completed the construction of their engineered biocells or at about 80%. These include Lots 022, 023, 024, 026, 029, 030, 031, 033, 034, 042, 043, 044, 045, 047, 048, 054 and 056. Five (5) other Lots (025, 046, 049, 050 and 053) are already at different stages of construction expecting completion soon.

Excavation of impacted soil has been completed in two (2) of the sites in Phase 1 Batch 2 remediation works while treatment and backfilling are at various stages of progression. Eleven (11) other Lots are at various stages of excavation and treatment of impacted soil while the remaining sixteen (16) are expected to commence same soon (see Table 2 below). Note: All quantities of free phase crude oil encountered during remediation works are always recovered, stored temporarily in safe reinforced plastic tanks on site and relinquished to asset owner before works are completed.

Table 3: Details of Status of Excavation Works at Lots in Phase 1 Batch 2 HYPREP Remediation Works.

Status of Excavation and Treatment WorksLot NumbersNumber of LotsSite(s)
COMPLETED026, 0432B.Dere/Gio in Gokana/Tai L.G.As and Aleto (Ngofa) in Eleme L.G.A respectively. Backfilling already started at Lot 043.
  ON-GOING022, 023, 031, 034   11B.Dere/Gio in Gokana/Tai L.G.As
030, 042, 044, 056Aabue Korokoro Flow Station in Tai L.G.A, Korokoro Well 4 in Tai L.G.A, Aleto (Ngofa) in Eleme L.G.A and New Elelenwo Manifold, Akpajo in Eleme L.G.A respectively.
047, 048, 054Okuluebu, Ogale in Eleme L.G.A.
    COMMENCING SOON024, 025, 032, 033   16B.Dere/Gio in Gokana/Tai L.G.As
027, 028Bara Alue in Tai L.G.A.
029Aabue Korokoro Flow Station in Tai L.G.A,
045Aleto (Ngofa) in Eleme L.G.A
046Nsioken, Akpajo in Eleme L.G.A
049 – 053, 055 (6 Lots)Okuluebu, Ogale in Eleme L.G.A.
057New Elelenwo Manifold, Akpajo in Eleme
  29 Lots 

Information on Status of Remediation Works of Phase 1 Batch 2 Sites summarized below:

 LOT NR. REMEDIATION CONTRACTOR SITE NAME L.G.A. STATUSPERFOR-MANCE PERCENTAGE (%)
 022Vitruvian Global Resources LtdB. Dere / GioGokana / Tai.Excavation and treatment of impacted soil.35
023Cascade Engineering Systems LtdB. Dere / GioGokana / Tai.Excavation and treatment of impacted soil.47
 024Levene Energy Dev LtdB. Dere / GioGokana / Tai.Construction of engineered bio-cell on-going.22
 025Subadom Global Resources LtdB. Dere / GioGokana / Tai.Site office set-up and construction of engineered bio-cell on-going.17
 026Earthquest Int’l LtdB. Dere / GioGokana / Tai.Excavation completed. Treatment of impacted soil on-going.73
 027Marm Consulting Services LtdBara AlueTaiCommunity leadership dispute which was hitherto delaying mobilization has been resolved. Contractors now starting activities.2
 028Emamed Nig LtdBara AlueTai4
029Weafri Well Services LtdAABUE Korokoro Flow Station (FS)TaiBio-cell construction on-going.19
 030Elizax Bleet Nig LtdAABUE Korokoro Flow Station (FS)TaiExcavation and treatment of impacted soil in progress.45
 031Oilserv LtdB. Dere / GioGokana / Tai.Excavation and treatment of impacted soil in progress.39
 032Mosito Environmental LtdB. Dere / GioGokana / Tai.Nil2
 033Christohouston Energy LtdB. Dere / GioGokana / Tai.Bio-cell construction on-going.22
 034DLK Oil & Gas LtdB. Dere / GioGokana / Tai.Excavation and treatment of impacted soil in progress.38
 042Kanny Koy LtdKorokor0 W-4 Tai.Excavation and treatment of impacted soil in progress.71
 043Otaoilf Services LtdAleto NgofaElemeExcavation completed, treatment and backfilling in progress.78
 044M/S Harrisco Int’l LtdAleto NgofaElemeExcavation of impacted soil.41
 045Chavyn Nig LtdAleto NgofaElemeCompleted bio-cell construction.25
 046Andelsta LtdNsioken AkpajoElemeBio-cell construction on-going.16
 047Lapideo Multi Services LtdAjeokpori W-3 OkuluebuElemeExcavation of impacted soil for treatment on-going.33
 048Slot Eng Nig LtdAjeokpori W-3 OkuluebuElemeExcavation of impacted soil for treatment on-going.35
 049Environ Consult & Remedial Service LtdAjeokpori W-3 OkuluebuElemeSite office set-up, bio-cell construction on-going.17
 050Klartek Nig LtdAjeokpori W-3 OkuluebuElemeSetting up of site office in progress.13
 051Erotina Nig LtdAjeokpori W-3 OkuluebuElemeSetting up of site office in progress.7
 052Montego Upstream Services LtdAjeokpori W-3 OkuluebuElemeSetting up of site office in progress.7
 053Atlas- Ray & Sons Coy LtdAjeokpori W-3 OkuluebuElemeCompletion of bio-cell construction.19
 054Brant Technologies LtdAjeokpori W-3 OkuluebuElemeCompletion of bio-cell construction, excavation of impacted soil in progress37
 055ADG Int’l Resources LtdAjeokpori W-3 OkuluebuElemeSite office set-up. 5
056Awa Engineering Coy LtdNew Elelenwo Manifold, AkpajoElemeExcavation and treatment of impacted soil at advance stage.53
 057Integrated Chemical Works LtdNew Elelenwo Manifold, AkpajoElemeSite office set-up in progress.4

STATUS OF PHASE 1, BATCH 1 AND BATCH 2 REMEDIATION PROJECT

STATUS OF PHASE 1, BATCH 1 SITES

             Active Phase 1 Batch 1 Lots

In the month of January 2021, remediation work was actively in progress at three (3) of the five (5) outstanding Lots in Phase 1 Batch 1 Remediation Project Lots/Sites.At Lot 009 (Saanako – Mogho, Gokana L.G.A), the contractor was engaged in movement of dredged sand from the project site to a section suitable for evacuation by the local sand dredger.

Plate 1: On-going relocation of dredged sand from the project area at Lot 009 (Saanako) in Mogho, Gokana L.G.A.

At Lot 012 (Debon-Bodo/ Mogho, Gokana L.G.A), the contractor Messrs. Shamsa Resources & Services Ltd undertook excavation and treatment of contaminated soil and backfilling of remediated soil. He achieved additional 20%, bringing his overall achievement of work done to 85%. Soil samples which were earlier taken from some sections of the site for Quality Assurance and Quality Control (QA/QC) by HYPREP for internal verification in NOSDRA accredited laboratory had returned showing considerable reduction in the levels of TPH in soil. Contractor has been authorized to backfill the clean trenches with treatedsoil

At Lot 013 (NweekolZorbuke Section A, K. Dere, Gokana L.G.A), the contractor Centennial Devt. & Investment Ltd achieved additional 25% of remediation work involving excavation and treatment of contaminated soil as well as backfilling of clean remediated soil. Soil samples from Section A2 of the site were taken for Quality Assurance and Quality Control (QA/QC) by HYPREP for internal verification in NOSDRA accredited laboratory.

Plate 3: Officers from the Operations Unit undertake QA/QC Monitoring Sampling in an excavated trench.

The other two (2) outstanding Phase 1 Batch 1 Remediation Lots, Lot 011 (Debon- Bodo/Mogho) and Lot 016 (Korokoro Well 005) are presently out of site awaiting completion of processes of Milestone payments.

         Detailed information of remediation work performance status

S/NLOT NRREMEDIATION CONTRACTORSITE NAMEL.G.A.PERFOR-MANCE PERCENTAGE (%)
1009Odun Environmental LtdSaanako, MoghoGOKANA41
2011Mosvinny Nig LtdDebon- Bodo / MoghoGOKANA84
3012Shamsa Resources &Services LtdDebon. Bodo / MoghoGOKANA85
4013Centennial Devt. & Investments LtdNweekolZorbuke, K.DereGOKANA80
5016Newline West Africa LtdBuemeneKorokoro Well005TAI56

Setting up of site offices had begun at twenty-two (22) out of the twenty-nine (29) Phase 1, Batch 2 remediation sites who just recently mobilized to site

Nine (9) of them (Lots 022, 023, 026,  030,  042,  043,  045, 054, 056 ) had  completed  the co n s t r u c t i o n of t h e i r Engineered Biocell with seven (7) others (Lots 031, 033, 044, 047, 048, 049, 053) are already a t  d i f f e r e n t  s t a g e s   o f c o n s t r u c t i o n e x p e c t i n g completion with.

Three (3) Phase 1, Batch 2 Remediation Lots (Lot 022 located in B/Dere-Gio, Gokana/Tai L.G.A, Lot 042 in Korokoro Well 004 in Tai L.G.A and Lot 043 located in Ngofa- Aleto site in Eleme L.G.A) have achieved varying levels of Excavation of impacted soil and subsequent treatment of excavated materials

Remediation work performance status of Phase 1 Batch 2 sites is summarized in Table 2 below:

LOT NRREMEDIATION CONTRACTORSITE NAMEL.G.A.STATUSPERFOR- MANCE PERCENTAGE (%)
022Vitruvian Global Resources LtdB. Dere / GioGokana / Tai.Excavation and treatment of impacted soil.35
023Cascade Engr SystemsB. Dere / GioGokana /Tai.Completion of biocellconstruction22
024Levene Energy Dev LtdB. Dere / GioGokana / Tai.Site office set-up5
025Subadom GlobalResources LtdB. Dere / GioGokana /Tai.Siteclearing/preparations3
026Earthquest Int’l LtdB. Dere / GioGokana / Tai.Completion of biocell22
027Marm Consulting Services LtdBara AlueTaiCommunity leadership dispute delayingmobilization0
028Emamed Nig LtdBara AlueTAICommunity leadershipdispute delaying mobilization0
029Weafri Well Services LtdAABUEKorokoroFlow Station (FS)TAISite clearing/preparations. Site office set-6
030ElizaxBleet Nig LtdAABUEKorokoro Flow Station(FS)TAICompletion of biocell construction25
031Oilserv LtdB. Dere / GioGokana / Tai.Siteclearing/preparations. Site office set-up14
032Mosito Environmental LtdB. Dere / GioGokana/TaiNillo
033Christohouston EnergyLtdB. Dere / GioGokana/TaiBiocell construction on-going.18
034DLK Oil & Gas LtdB. Dere / GioGokana/TaiSite clearing/preparations. Site office set-up5
042KannyKoy LtdKorokor0 W-4TaiExcavation of impactedsoil.33
043Otaoilf Services LtdAletoNgofaElemeExcavation and treatment of impacted SOIL.55
044M/S Harrisco Int’l LtdAletoNgofaElemeCompletion of biocellconstruction21
045Chavyn Nig LtdAletoNgofaElemeCompleted biocell construction.25
046Andelsta LtdNsioken AkpajoElemeSite clearing/preparations. Site office set-up, biocell construction going,8
047Lapideo Multi Services LtdAjeokpori W- 3 OkuluebuElemeCompletion of biocell construction.22
048Slot Eng Nig LtdAjeokpori W-3 OkuluebuElemeCompletion of biocellconstruction.23
049Environ Consult & Remedial Service LtdAjeokpori W- 3 OkuluebuElemeSite office set-up, biocell construction going,17
050Klartek Nig LtdAjeokpori W-3OkuluebuElemeNil2
051Erotina Nig LtdAjeokpori W- 3 OkuluebuElemeNil.0
052Montego Upstream Services LtdAjeokpori W- 3 OkuluebuElemeNil.0
053Atlas- Ray & Sons Coy LtdAjeokpori W- 3 OkuluebuElemeCompletion of biocell construction.19
054Brant Technologies LtdAjeokpori W- 3 OkuluebuElemeCompletion of biocell construction.25
055ADG Int’l Resources LtdAjeokpori W- 3 OkuluebuElemeSiteclearing/preparations. Site office set-up.5
056Awa Engr Coy LtdNew Elelenwo Manifold, AkpajoElemeSite clearing/preparations. Site office set-up, biocell construction going,25
057Integrated Chemical Works LtdNew Elelenwo Manifold, AkpajoElemeSite clearing/preparations. Site office set-up.4

ON-THE-SPOT ASSESSMENT OF CONTRACTORS’ PERFORMANCE AT SITE

To ensure that HYPREP Contractors are carrying out the remediations works according to specification and in line with best international practice, the Head of Operations overseeing the Project Coordination Office, Prof. Philp Shekwolo led HYPREP team on an inspection visit to active sites in Phase 1, Batch 2 remediation in order to assess the performance of the Contractors at the sites on 29th January 2020.

As at the time of the visit, works were progressing steadily and according to HYPREP specification; however, Prof. Shekwolo urged the contractors to take advantage of the good weather condition by increasing their pace of work before the rains set in. He also used the opportunity to appeal to the host communities to continue to support the project and not to indulge in acts of sabotage.

The contractors were happy with the visit and promised to ensure that the quality of work is not compromised.

RESTORATION OF MANGROVE IN OGONILAND

STRATEGY FOR IMPLEMENTATION

A virtual meeting on ‘Strategy for the implementation of Mangrove Restoration was held on Wednesday 27th January 2020 where the Project Coordination Office was the host. The Meeting which began at about 1:15 p.m. had in attendance the underlisted

S/NPARTICIPANTORGANIZATION
1Prof. Philip D. ShekwoloHYPREP
2Mike CowingUNEP
3Dr. Ferdinand GiadomUNEP
4Chris NewsomSDN
5Calvin LaingSDN
6Ehiyokenegha ClarkSPDC
7Vincent NwabuezeSPDC
8Kabir YusufFME
9Sanusi AbubakarFME
10Isa WasaHYPREP
11Sampson EbimaroHYPREP
12Obarifomi John-OkpabiHYPREP
13OnisoweiyaEmemHYPREP

The purpose of the meeting was to discuss the Strategy for HYYPREP’s Implementation of Mangrove Restoration and Management in Ogoniland proposed by Prof. Philip D. Shekwolo, the Head of the Operations overseeing the Project Coordination Office, HYPREP. Prof. Philip Shekwolo gave a breakdown of his proposal which was discussed by the participants:

A.    Set-up of Shoreline Cleanup Assessment Team (SCAT)

Prof. Shekwolo proposed that the SCAT team, which is to carry out a ground survey of the area to be restored will consist of 2 members of the following stakeholder groups:

  • HYPREP (Host)
  • UNEP
  • FME
  • RSME
  • SPDC
  • SDN/CHERD
  • FRIN
  • NOSDRA
  • MOSOP
  • KAGOTE

Concerns about the logistics for mobilizing the team to the field and the representation of the Ogoni community by 2 different bodies, were raised. For the logistic for mobilization of the team, Prof. Shekwolo said that HYPREP would be responsible, and that the cost for the logistics has been captured in the HYPREP 2021 budget.

On the representation of the Ogoni community by 2 organizations, it was decided that MOSOP and KAGOTE will be merged to provide 2 representatives, one (1) from each organization. The total number of members of the SCAT team was thus reduced from 20 to 18. The field team, however, will also include some other persons who are not members of the SCAT team, like security personnel and community guides.

A.    Terms of Reference (ToR)

Stoppage of artisanal refining: It was pointed out that the team’s efforts can only be contributory as this is an area where even the government has not had a lot of success so far.Timeline & Timing: The entire restoration of the mangrove is a multi-year project and the timeline should be reflected as such in the proposal. The 6-months timeline for the scoping period is to be reflected in the proposal as well.

An issue with the timing of the project was raised by Mr. Nwabueze, he said that it might be too soon to begin the mangrove restoration project since the upland remediation is still on- going and the work has not yet begun on the Category A sites, hence the workload might be overwhelming. In response Prof. Shekwolo said that it is essential to begin work on the eyesore areas like the mangroves as they have more visual impact and would help restoring the people’s faith in HYPREP’s activities; these activities can be run con-currently. It was also noted by Mr. Clark of SPDC that the ToR did not include a mechanism for reflecting the learnings from previous similar projects.

A.    Deliverables

Responsibility Ownership: It was made clear that the overall execution project is owned by HYPREP and the SCAT team will just be contributing.It was agreed that since the SCAT scoping exercise would last for 6 months, the deliverables for that activity should be adjusted to fit in that timeframe.

B.    Approach and Modalities

It was suggested that the method for tackling the artisanal refining be reconsidered. The proposal is to be submitted to the Governing Council (GC) of HYPREP for approval, but because the GC has not been reinstated, it was pointed out that the timeline might need to be reviewed.

Reference
https://hyprep.gov.ng/remediation-work/

.